GO TO PREFACE GO TO PURPOSE TO TOOLS & MATERIALS ACTIVITIES TO SAFETY TO TIPS/TRICKS TO GLOSSARY  
CRAFT HOME
CRAFT MODULES
MODULE ONE
MODULE TWO
MODULE THREE
MODULE FOUR
 
 
SPONSORS
REFERENCES
SUPPLIERS
 

<--Back to ACTIVITIES Menu | Activities: 01 | 02 | 03 | 04 | 05 | 06 | 07 | 08 | 09 | 10 | Next -->

Module Two - Activity 6 - Building a Semi-Permanent Tower

The semi-permanent tower described here is made of sturdy, pre-manufactured materials. It is fairly simple to erect though it does require some effort. The advantage of this tower type is that it is fairly tall, should be able to serve an entire community, and can be erected with little change to the environment. The key to easily creating a semi-permanent tower such as the one in this example, is to do as much of the work as possible while the tower is still on the ground.



      

Base: To begin, create the tower base that will serve as a sturdy mounting point for the structure. The base should be at least 2'-0" long by 2'-0" wide by 1'-0" deep. It should be dug into the ground, and should be of solid concrete.

Saw some 2x8" boards to create a form for the base, as shown. Nail the boards together very well. Next, dig a hole large enough for the form to fit into. The form should sit in the hole so that the top of the form is level with the ground, however the centre of the hole should be deeper than the form itself, as shown.

Next, mix, using the instructions on the bag, enough cement mix with water to fill the form. If there are some large rocks around, these can be put into the hole to save on cement, as long as there is enough cement to bind the entire base together. (i.e. not TOO many rocks.)

Once the form is filled, agitate the cement to ensure that it has properly settled into the form. Next, smooth off the top nicely using a board or a cement finishing tool.




      

Place the base-plate onto the wet concrete, arrange it in the correct orientation according to the direction that you would like the finished tower to be oriented. Note where the bolt holes need to be. Remove the baseplate, and push the baseplate anchorbolts into the wet concrete. Slide the baseplate over the anchorbolts, level it in place, wipe the tops of the anchorbolts free of any concrete residue, and screw the nuts into place on the anchor bolts.

Leave the form to set for the recommended time period. If the concrete is kept wet while it is curing, the cure will be stronger than if it is allowed to set in completely dry conditions. Dryer conditions during concrete setting makes a more brittle finished product.




      

Prepare tower sections: Scrape and sand individual tower sections and slip-up poles as required to remove any debris. Paint all tower sections with at least two coats of spray paint prior to assembly. This step will ensure that the tower lasts longer, and should be done even if the tower sections are pre-treated (galvanized.)

TIP: Even if the tower sections are already galvanized, sand and paint them with a couple of coats of spraypaint before you put the tower up. It will last much longer, especially in poor weather conditions.
Click here for a short film
demonstrating how to prepare the tower
( 830 kb download).



Assemble tower parts: Using a file, remove any burrs from the metal to avoid scrapes, then slip the tower pieces together. Bolt them firmly into place. It is a good idea to use large eyebolts for bolting together multi-section towers as this allows a firm attachment point for the guywires.

 

 

The top mast generally has a specific place where it is attached. It fits through a triangular plate where it is affixed with a U-bolt clamp as shown.


TIP: Use eye bolts instead of regular bolts when putting the tower together. This will give you a firm, smooth attachment point for the guylines.

Attach guy wires: Three guy wires are required for every ten feet of tower height. Each guy attachment requires two clamps, for safety and reliability of the attachment point. This ensures that there is no weak spot in the tower support system. When affixing the clamps, it is best to orient them in the opposite direction to one another. Once affixed, tape over the end of the trimmed guywire, and both of the clamps, with a double layer of electrical tape.

     

Each guy wire must be terminated with a turnbuckle at the guyline endpoint. Special clamps are available if guys are to be attached to chainlink fences. This is a common practice, as many antenna surrounds are fenced in. If a secure mounting point such as a fence is not available, guys may be secured by burying a deadman anchor, or a large rock or log with a chain around it, to which the guys may be attached.

 





      

Assemble tower parts: Using a file, remove any burrs from the metal to avoid scrapes, then slip the tower pieces together. Bolt them firmly into place. It is a good idea to use large eyebolts for bolting together multi-section towers as this allows a firm attachment point for the guywires.

Next, lay out the LMR 400 waveguide cable alongside the tower in preparation for attaching the antenna(s).

TIP: Use TWO guywire clamps at each end. This will eliminate weak spots.


Attach Attennas to mast: Use the clamps and fittings provided with the antenna, and loosely attach it in its approximate final orientation. Antennas are loosely attached at first so that they can be easily moved around and fastened firmly only once they are in the best orientation. If more than one antenna is being mounted, they should be placed at least ten feet apart. However, if both are on the same network, this is less of an issue.

Shown being mounted in the picture at the left are an omni directional antenna, and a directional antenna.


Above: Omni directional antenna mounted at the top of the mast.
Below: Covered directional Yagi antenna mounted further down the tower mast.

The omni directional antenna is used to deliver a signal locally within the small community where this installation is being created, whereas the directional antenna is used for backbone connectivity to an antenna mounted at a nearby TV tower.



Fasten the antennas to the LMR 400 Waveguide: Place a bead of silicone along the threads of the LMR 400 waveguide connector, and screw the two connector halves together.

TIP: Use a bead of silicone when screwing together waveguide connectors - this will ensure that they seal properly and may help the network last longer!

Once together and tightened finger-tight, finish tightening the connectors together, finish tightening the connection using a wrench.

Next, wrap two layers of electrical tape over the connection, from the bottom up, so that water will run off the joint. See below - the taped joint is later secured directly to the tower using tiestraps wrapped with a layer of electrical tape as UV protection.

If more than one antenna is being mounted, take the time at this point to carefully label the antennas and the corresponding waveguide, using a label machine. If a label machine is not available, mark the antennas and waveguide clearly in another way, (spraypaint, electrical tape around one of the antennas and waveguides, surveyors tape, etc - whatever is handy that will work) so that if there is a problem at some point, it will be obvious from the ground which waveguide belongs with which antenna.


Firmly affix the wave guide to the tower: Next, tie strap the waveguide cable along the entire length of the tower, every 18". Also, tape well at any potential abrasion points, such as near guy wires. Try to eliminate the possibility for abrasion by ensuring that the waveguide is fastened well enough that it can't come into contact with guylines or other potentially harmful surfaces during rough weather.

If the tie-straps are attached above the cross-members, they will not slide down. Then, to protect the tiestraps from UV light and weather, wrap them with a layer of electrical tape. With the tower together, the antennas affixed and the waveguide firmly attached as shown, the tower is now almost ready to tip up.



Affix a danger sticker as shown prominently to the lower part of the tower at eye level.

Now the tower is ready to be lifted, HOWEVER, before doing so, stop to inspect the site.

People are killed and injured every year trying to install towers and antennas. Take some time to think, and make sure that you won't be one of them.

  • Look around, remove any obstacles that could be tripped on.

  • Check again to make sure power lines are FAR away. Always assume that ANY overhead lines can kill you.
    Avoid overhead lines. Period.

  • If the tower is being raised by a group of people, assign each person a specific task, including a leader who will co-ordinate the operation. One person should be a spotter to watch for and warn the others of potential problems.

  • WEAR APPROPRIATE SAFETY GEAR!!! Hardhats, STEEL-TOED SHOES WITH RUBBER SOLES, gloves, safety vests, long sleeves and long pants.

  • If the tower starts to drop, let it fall, and GET OUT OF THE WAY!!!! Don't try to save it. It's a lot bigger than you are, and it's replaceable.

  • If the tower comes into contact with an electrical wire (which it SHOULD NOT, if the installation is correctly planned), DO NOT TOUCH IT. Secure the area, get everyone out of the way, and call a power crew to help.


Raising the tower: Raise the tower slowly, using a co-ordinated effort, with plenty of communication.

First, lift the tower and orient it in the correct direction.


 



Next, have one person hold the tower while the others untangle or free the guywires, and make sure that the waveguide will not be crushed while raising the tower.





 



Lift and guide the tower: Have one person guide the tower base towards the base plate as the other people lift the tower, gradually walking their hands up the tower "ladder".






 



Steady the tower and bolt it down: When the base of the tower is in place, have several people steady the tower while one person (or two people) inserts the bolts that will hold the tower in place.



     

Left: bolting the tower in place, Right: bolting complete.

 



GUY wires: With the tower firmly bolted in place, it is now possible to attach the guy wires:

  • Put the safety flagging over the guy wire FIRST.


    TIP: If you don't have the proper safety flagging, yellow garden hose works just as well.

  • Next, install the clamp, deadman, or peg to which the guyline will be attached.
  • Lastly, pull the guyline through a TURNBUCKLE, loosely at first, then gradually tighter as all guylines are being adjusted. Clamp them into place using TWO clamps.
  • Even up the tension on all guy wires PRIOR to doing a final tightening on all guys.
  • Cut guy wire ends to length.
  • Wrap guy wire ends and clamps with a layer of electrical tape, from the bottom up to ensure that water will run off.
  • Pull the flagging down as far as it will come, so that it is visible near the bottom of the guy wires where people may run into it!


Fasten antennas: With the guy wires fastened, it is now safe to climb the tower to do the final orientation and fastening on the antennas.

  • Wear a safety harness, hard hat, and other protective gear.
  • Take binoculars with you so that you can double-check the line-of-sight if required.

  • Pay attention to the polarity of the antenna, making sure that it is installed according to the specifications for the specific antenna.
  • Take enough tools with you, and a crescent wrench for good measure!
  • DO NOT climb the tower if it is WINDY, RAINY, SNOWY, ICY, or if other bad weather conditions are present which could make you fall.


    If there isn't time after installing the tower to set up the equipment, make sure that you coil and tape the waveguide safely in place so that it doesn't get run over or damaged in any way. Check to make sure that the structure is safe before leaving it.



The tower is now COMPLETE!
It's ready for you to create an equipment enclosure, and hook
up the wireless networking equipment.